Strata EV Charging Infrastructure: How to Make Your Building Fleet-Ready

Summary: Making a strata building EV-ready typically costs $2,000–$5,000 per parking space for electrical infrastructure (sub-metering, cable trays, distribution boards) plus $1,500–$3,500 per charger installed. NSW grants cover up to $3,000 per AC charging port through the Kick-start program. A load management system (LMS) allows 10–20 chargers to share existing electrical capacity without expensive supply upgrades, reducing per-space costs by 40–60%. Strata corporations should start with a building electrical capacity assessment, then install shared infrastructure that individual lot owners can connect to over time.

By · · Updated · 9 min

The Strata EV Problem — And Why It's Urgent

Here's the reality facing every strata manager in NSW: the Electric Vehicle Council's 2026 report projects that 50% of new car sales will be electric by 2030. In a 100-unit building, that means 50+ residents will need charging within four years.

Buildings that aren't prepared face three compounding problems:

  1. Ad-hoc installations — Individual owners hiring their own electricians, creating safety risks and overloading circuits
  2. Declining property values — Buyers increasingly filter for "EV-ready" buildings on real estate platforms
  3. Expensive retrofits — Installing infrastructure reactively costs 2–3× more than a planned rollout

"The single most expensive mistake we see in strata is waiting. A building that installs shared cable trays and a distribution board today spends $1,500 per space. The same building doing it in 2029, after 15 individual owners have run cables through fire compartments, spends $4,000+ per space to remediate and standardise." — Daniel Harris, Licensed Electrical Engineer, Cable Co

What "EV-Ready" Actually Means for Strata

The NSW Government's EV Ready Buildings program defines three levels of readiness:

LevelDefinitionWhat's InstalledCost Per Space
EV-CapableElectrical capacity reserved, pathway identifiedConduit/cable tray only$500–$1,000
EV-ReadyWiring to parking space, circuit protection installedCable, DB, metering$2,000–$3,500
EV-InstalledCharger connected and operationalFull charger + infrastructure$3,500–$6,000

For most strata buildings, the optimal strategy is to install EV-Ready infrastructure for all spaces (or a percentage), then allow individual owners to add chargers as needed. This approach:

  • Shares the major infrastructure cost across all owners (via special levy or sinking fund)
  • Prevents ad-hoc installations that create safety hazards
  • Qualifies for NSW government grants
  • Maximises property value uplift for all units

The Load Management Solution: 20 Chargers on Existing Supply

The biggest fear strata committees have is: "We'll need a $200,000 supply upgrade from Ausgrid." In most cases, this isn't true.

A Load Management System (LMS) dynamically distributes available electrical capacity across all connected chargers. When the building's base load is high (evening cooking, air conditioning), chargers reduce power. When load drops (overnight), chargers ramp up.

How LMS Changes the Economics

ApproachChargers SupportedSupply Upgrade NeededCost
No LMS (dedicated circuits)3–5Usually yes ($50k–$200k)$15,000–$25,000 per charger
With LMS (shared capacity)15–30Usually no$3,000–$5,000 per charger

Cable Co installs Origin Energy's Load Management System as part of our Origin Preferred Commercial Partner program. The system supports up to 40 chargers per building on a single LMS controller.

NSW Grants for Strata EV Charging

Kick-start Funding (For Strata Corporate Vehicles)

If your strata corporation operates vehicles (building management, caretaker vehicles), you can claim:

  • $5,000 per BEV purchased
  • Up to $3,000 per AC charging port installed

EV Ready Buildings Program

The NSW Government's EV Ready Buildings program provides guidance and support for strata buildings planning EV infrastructure. Check the program page for current funding rounds.

Destination Charging Grants (For Visitor/Shared Chargers)

If your building installs publicly accessible chargers (visitor parking, shared resident chargers), you may qualify for the Destination Charging Grant — up to 75% of installation costs.

Step-by-Step: Making Your Building EV-Ready

Step 1: Electrical Capacity Assessment

Before anything else, you need to know what your building's electrical supply can handle. Cable Co performs a detailed assessment including:

  • Main switchboard capacity and spare ways
  • Existing load profile (24-hour monitoring)
  • Available capacity for EV charging (kW headroom)
  • Cable pathway options to car park
  • Fire compartment and compliance considerations
  • Use our Strata Compliance Cost Calculator for an instant estimate of your building's assessment and infrastructure costs.

Step 2: Design the Shared Infrastructure

Based on the assessment, we design a shared infrastructure solution:

  • Distribution board in car park (dedicated EV circuits)
  • Cable trays running to parking bays (shared pathway)
  • Sub-metering for individual billing (each owner pays for their own electricity)
  • Load management system to prevent overload
  • Future-proofing — capacity for 100% of spaces over time

Step 3: Strata Resolution and Funding

EV charging infrastructure typically requires a special resolution (75% vote) at a general meeting. We provide:

  • Technical report for the strata committee
  • Cost breakdown and funding options (special levy vs sinking fund vs owner-pays)
  • Comparison of approaches (shared infrastructure vs individual installations)
  • Grant application support

Step 4: Installation and Commissioning

Cable Co handles the complete installation:

  • Licensed electricians (NSW Fair Trading)
  • ASP accredited (for any supply upgrade work)
  • Ausgrid/Endeavour approved
  • Fire safety compliance (AS/NZS 3000)
  • Commissioning and testing of all circuits
  • LMS configuration and monitoring setup

Step 5: Ongoing Management

Post-installation, we provide:

  • Charger monitoring and fault alerts
  • Preventive maintenance program
  • Billing system management (per-owner metering)
  • Expansion support as more owners add chargers

What It Actually Costs: Real Strata Projects

Building SizeSpaces Made EV-ReadyInfrastructure CostPer-Space CostGrant Offset
20 units10 spaces$35,000$3,500$15,000–$30,000
50 units25 spaces$75,000$3,000$37,500–$75,000
100 units50 spaces$130,000$2,600$75,000–$150,000
200 units100 spaces$220,000$2,200$150,000–$300,000

With grants, the net cost to the strata corporation can be as low as $500–$1,500 per space — easily funded through the capital works fund over 2–3 years.

Frequently Asked Questions

Does a strata building need a special resolution for EV charging?

In most cases, yes. Installing shared EV infrastructure in common property requires a special resolution (75% of votes at a general meeting) under the Strata Schemes Management Act 2015 (NSW). Individual lot owners installing chargers in their own lot may only need committee approval, depending on the by-laws.

Can individual owners install their own chargers without building-wide infrastructure?

Technically yes, but it's strongly discouraged. Individual installations often create safety hazards (cables across fire compartments), overload existing circuits, and cost 2–3× more per owner than a shared infrastructure approach. Most strata committees now require a building-wide plan before approving individual installations.

How does billing work when multiple owners share infrastructure?

Each charging point is individually sub-metered. Owners pay for their own electricity consumption, typically billed monthly through the strata management system or a third-party billing platform. The shared infrastructure cost (cable trays, distribution boards, LMS) is funded through the capital works fund or a special levy.

Will EV charging increase my building's insurance premiums?

Not if installed correctly by a licensed electrician to Australian Standards (AS/NZS 3000). Cable Co provides compliance certificates for all installations. Some insurers offer discounts for buildings with professionally installed, monitored charging systems.

How long does a strata EV infrastructure project take?

Typical timeline: 2–4 weeks for assessment and design, 4–6 weeks for strata approval process, 2–4 weeks for installation. Total: 2–3 months from initial enquiry to operational chargers.

Frequently Asked Questions

How much does strata EV charging infrastructure cost per parking space?

Making a strata parking space EV-ready costs $2,000–$5,000 for shared infrastructure (cable trays, distribution board, sub-metering) plus $1,500–$3,500 for the charger itself. With NSW grants covering up to $3,000 per port, net costs can be as low as $500–$1,500 per space.

Do strata buildings need a supply upgrade for EV charging?

Usually not, if a Load Management System (LMS) is installed. An LMS dynamically distributes available electrical capacity across all chargers, allowing 15–30 chargers to operate on existing building supply without expensive upgrades from Ausgrid or Endeavour Energy.

What strata resolution is needed for EV charging installation?

Installing shared EV infrastructure in common property typically requires a special resolution (75% of votes) at a general meeting under the Strata Schemes Management Act 2015 (NSW). Individual lot owners may only need committee approval depending on the building's by-laws.

Can strata buildings get government grants for EV charging?

Yes. NSW offers up to $3,000 per AC charging port through the Kick-start program (for strata corporate vehicles), destination charging grants (up to 75% for publicly accessible chargers), and the EV Ready Buildings program for planning support.

How many EV chargers can a strata building support without upgrades?

With a Load Management System, most strata buildings can support 15–30 chargers on existing electrical supply. Without LMS, only 3–5 dedicated chargers are typically possible before a supply upgrade is required.